De - Shuttering Period
15' / 4.5 m slab = 10 days
15' more slab = 14 days
20' / 6 m beam = 14 days
20' / 6 m more beam = 21 days
Column, beam side = 1 - 2 days
* Water and Sanitary work
Type of pipe Grade of pipe Color of pipe
Light weight A Yellow
Medium weight B Blue
Heavy weight C Red
Types of pipes in the market:-
G.I, C.I, P.V.C etc.
* Measurements of pipes which are used in plumbing:-
Pipe Work Dia. of Pipe
Toilet - 4'' dia.
Kitchen, bath room - 3'' dia.
Ventilation pipe - 2'' dia.
Inlet & outlet pipe - 1'' dia.
Other - 1 / 2 '' dia.
Bathroom Fitting
(a) Wash basin
(b) Shower
(c) Bath tub
* Cement sand ratio for plaster
1 : 4 or 1 : 6
1 = 1 bag cement
4 = 4 bag sand
Curing of water should be minimum one week.
* Floor
For Tiles
Before placing of tiles, the mixture of cement and sand fill at 75 to 100 mm. The slurry of cement paste on the back side of tiles, then place the tiles.
For Marbles
1 st grinding the marbles and polish it.
* Wood
Types of wood:-
(a) Devdar
(b) Shisham
(c) Verma
(d) Tik etc.
* Paint
After the plaster :-
Putty of the wall, then double core putty and rub them to the sand paper. Then we use primer, then we use color.
Types of pipe in the market :
G.I, C.I, P.V.C etc.
The companies names which provides better quality of pipes as Tata, Jindal, J.T.L, Nico etc.
Measurements of pipe which are used in plumbing
* Bathroom fitting
(a) Wash basin
(b) Shower
(c) Bath tub
* Cement, Sand ratio for plaster
1 : 4 or 1 : 6
1 = 1 bag cement
4 = 6 bag sand
Curing of plaster should be almost minimum one week.
* Floor
For Tiles
Before placing of tiles, the mixture of cement and sand fill at 75 mm to 100 mm. The slurry of cement, paste on the back side of tiles, then place the tiles.
For Marbles
1st grading the marbles and polish it.
* Wood
Types of wood :-
(a) Devdar
(b) Shisham
(c) Verma
(d) Tik etc.
* Paint
After the plaster -
putty of the wall, then double core putty, after that rub them to the sand paper. Then we use primer, color.
You have any dought, let me know.